INVENTORY ASSESSMENT AND PROJECT SUPPORT |
|
Project
Support:
American
Servoil
provides procurement support and materials management to
engineering design and construction companies.
Here are some of the projects we have supported:
|
|
|
|
Inventory
Assessment Services
|
|
Marathon
Oil Gabon, Gabon
|
|
- Complete
inventory assessment, including overhaul of material management
Processes and Procedures. Identification and segregation of surplus,
cataloging of all Materials in proper nomenclature & description
format, perform 100% inventory, Re-organize pipe yard and warehouse,
consolidation of three different material control Systems &
databases into one (MP2), and provide training. Staffing Provided - Sr.
Material Management Consultant, Robert Peck Material Systems Specialist,
Mike Foucheux Material Control Specialist, Billy Delk
|
|
Dec.
2002 – April, 2003
|
|
Offshore
Platform and Pipeline
|
|
Marathon
Oil Gabon, Gabon
|
|
- Material
Management/Export-Import Coordination, field material control, logistics
Support Staff Provided - Material Control Specialist, Billy Delk
Material Logistics Coordinator, Connel Shelton
|
|
June.
2002 – Dec. 2002
|
|
Inventory
Assessment Services
|
|
TotalFinaElf
E&P Indonesia
|
|
- Inventory
and assessment of all Construction and Drilling & Well Completion
materials. Including cataloging of all materials in a proper
nomenclature & description format and Reorganizing materials.
Identification of surplus and cataloging of unlisted materials. Onsite
training of local TFE staff. Install barcode labeling system. Staffing
Provided - Project Manager, Robert Peck Material Control Specialist,
Billy Delk Material Systems Specialist, Mike Foucheux Local Material
Control Support, 5 persons with Degrees
|
|
Sept.
2001 – June 2002
|
|
Offshore
Platform; T-West Gabon
|
|
Marathon
Oil
|
|
|
|
July
2000 – Jan. 2001
|
|
Offshore
Platform & MOPU - Gabon
|
|
CBS
Engineering/Marathon Oil
|
|
- Material
Management/Export-Import Coordination/Field material control/Logistics
support/Material review. Operations support. Staffing Provided - Sr.
Material Management Consultant, Robert Peck Material Control Specialist,
Billy Delk Material Logistics Coordinator, Connel Shelton Material
Logistics Coordinator, Mike Foucheux
|
|
Jan.
1999 – June 2000
|
|
Pipe
Coating Plant – Usinsk, Russia
|
|
Jetair
International/Itochu
|
|
- Purchasing/Materials
coordination/Inspection coordination/Export coordination. Staffing
Provided - Sr. Material Management Consultant, Robert Peck Material
Logistics Coordinator, Connel Shelton Material Control Specialist, Billy
Delk Sr. Buyer, Vicky Lang
|
|
Nov.
1997 – Oct. 1998
|
|
LNG
Upstream Project – Trinidad
|
|
Amoco
Trinidad Oil Company (now BP)
|
|
- Two
Offshore Platforms, Onshore-Offshore Pipelines, New Onshore Facilities
Materials Management/Consulting/Material Control/Export-Import
Coordination Client considered Servoil's support of this Project as a
"Best Practice". Staffing Provided - Sr. Material Management
Consultant, Robert Peck Contracts Specialist, Jack Hampton Material
Control Specialist, Billy Delk Material Logistics Coordinator, Connel
Shelton Sr. Material Control Specialist, Burke Aziz Material Control
Specialist, Trevor Chin Hong Additional Misc. local support staff, 4
persons
|
|
March
1997 – Oct. 1998
|
|
Soil
Remediation Units
|
|
OnSite
Technology
|
|
- New
technology environmental remediation equipment. Complete procurement and
material management support. Staffing Provided - Sr. Material Management
Consultant, Robert Peck Material Logistics Coordinator, Connel Shelton
Buyer, Vicky Lang
|
|
Aug.
1996 – July 1997
|
|
Enchilada
Platform
|
|
Shell
Offshore/Alliance Engineering
|
|
- Offshore
Platform/Pipeline – Gulf of Mexico
RFQ Packages/Bid - Evaluations/Purchase
Orders/Expediting/Vendor Data Control Staffing Provided - Procurement
Manager, Robert Peck Sr. Buyer, Connel Shelton Sr. Documentation Clerk,
Denise Johnston Documentation Clerk, Vicky Lang
|
|
Oct.
1995 – Feb. 1998
|
|
|
|
|
Salsa
Platform
|
|
Shell
Offshore/Alliance Engineering
|
|
- Offshore
Platform/Pipeline - Gulf of Mexico RFQ Packages/Bid Evaluations/Purchase
Orders/Expediting/Vendor Data Control Staffing Provided - Procurement
Manager, Robert Peck Sr. Buyer, Connel Shelton Sr. Documentation Clerk,
Denise Johnston Documentation Clerk, Vicky Lang
|
|
Aug.
1996 – Dec. 1997
|
|
Tantawan
Development Project
Thailand – Two Offshore Platforms, One FPSO
|
|
POGO
Producing/Alliance Engineering
May
1995 – March 1996
|
|
- Bidder
Lists/RFQ Packages/Vendor Data Control/Data Books Staffing Provided -
Procurement Manager, Robert Peck Sr. Buyer, Connel Shelton Sr.
Documentation Clerk, Denise Johnston
|
|
|
|
Cassia
Upgrade Project
|
|
Amoco
Trinidad Oil Company (now BP)
|
|
- Offshore
Platform Upgrade Complete Procurement and Material Management Support.
Material control. Staffing Provided - Procurement / Project Manager,
Robert Peck Logistics Specialist, Connel Shelton Sr. Buyer, Pete Miniyev
|
|
Aug.
1995 – Dec. 1996
|
|
Banyan
Project
|
|
Amoco
Trinidad Oil Company (now BP)
|
|
- Offshore
Platform/Pipeline Complete Procurement and Material Management Support
Staffing Provided - Procurement / Project Manager, Robert Peck Sr.
Buyer, Pete Miniyev Expediter / Material Control, Denise Johnston
|
|
June
1994 – Feb. 1995
|
|
|
|
|